|
Journal
Date & Hours
|
Journal
|
Journal
Photo
|
|
Date: 2000
|
This year was for planning. Colin completed
on thesis on designing and building a sustainable home. This was
the groundwork for our own home.
Recycled timbers were sourced from demolition
yards, auctions and businesses that specialise in trading second
hand products.
Recycled railway sleepers were a perfect
solution for bearers and joists on the utility deck. These decks
will carry 54000 litres of stored water.
|


|
|
|
|
|
|
Date:
Jan '01
Building Hours: 43
|
Holes for the house poles were dug using
elbow grease and a jackhammer.
Chris breaking the soil ... then Col took
over.
|

|
|
|
|
|
Date:
Jan '01
Building Hours: 57
|
The Newton House structure is based around
recycled turpentine marine pylons. These were initially from a
jetty on Horn Island, Qld.
Chris purchased them at an auction. A
crane was used to place the poles into the holes.
|

|
|
|
|
|
Date: Jan - March '01
Building Hours: 122
|
Chains, hand winch and tirfor were used
to plumb each of the poles.
The poles were up to 13 meters long with
diameters 350 to 600mm.
|

|
|
|
|
|
Date: Jan - March '01
Building Hours: 122
|
The natural rock and soil was rammed back
in, layer at a time, using a crow bar.
This job is always more satisfying when
shared with a friend... thanks Ross.
|

|
|
|
|
|
Date: April'01
Building Hours: 223
|
Sub floor posts were off cuts also purchased
at auction.
|
|
|
|
|
|
Date:
May '01
Building Hours: 299
|
Pre-drilling for the bolts. Peter traveled
up from Tasmania to be part of this project.
|
|
|
|
|
|
Date:
May '01
Building Hours: 356
|
The utilities' deck starts to take shape.
This floor will hold the 3 water tanks; dry composting toilet
bins and the grey water system.
It could also hold a diesel locomotive,
but Chris hasn't found one at the auctions yet.
|
|
|
|
|
|
Date: June'01
Building Hours: 444
|
The hardwood sleepers are seconds; the
imperfections in these will be lost under the water tanks that
will go on top of the decks.
Zincalume steel capping over the bearers
will improve their durability, as the decks will be exposed to
weather. The capping were previously used on bessar block walls
- they were sourced from the local tip.
|
|
|
|
|
|
Date: June'01
Building Hours: 444
|
Halfway there
6 poles in and the
decking on. We now needed to place another 5 tall poles and extend
the deck out to meet them. So here we go.
|
|
|
|
|
|
Date: July '01
Total Building Hours: 496
|
We dig the holes
the crane places
the poles in the holes
|
|
|
|
|
|
|
Date: July '01
Total Building Hours: 533
|
the poles are plumbed using chains
and pulleys
and we ram them into position.
|
|
|
|
|
|
Date: July '01
Total Building Hours: 533
|
We now have 11 tall poles in position,
and half the deck complete.
|
|
|
|
|
|
Date: July '01
Total Building Hours: 606
|
Seasoned hardwood poles, bearers and railway
sleepers are shaped together.
|
|
|
|
|
|
|
Date: Sept '01
Total Building Hours:960
|
The hours spent on the detailing with these
old timbers has made timeless features.
|
|
|
|
|
|
Date: Sept '01
Total Building Hours: 960
|
Utilities Deck Completed.
|
|
|
|
|
|
Date: Aug '01
|
Meanwhile Chris is continually keeping
her eyes open for appropriate opportunities and second hand products
that will suit our lifestyle and the design of our home.
This old Turkish marble basin will become
our vanity sink....
... and this fallen red gum stump will
be our bath tub.
|


|
|
|
|
|
Date: Oct '01
Total Building Hours: 1008
|
The first bearer for the next floor is
profiled and pre-drilled before it is lifted into place using
pulley blocks.
|
|
|
|
|
|
Date: Oct '01
Total Building Hours: 1030
|
Shear blocks are made for each bearer to
sit onto. Another use for the old railway sleepers.
|
|
|
|
|
|
Date: Nov '01
Total Building Hours: 1196
|
Then add the bearers.
These were individually profiled before
being lifted into place using the pulley blocks...
|
|
| |
|
|
|
Date: Nov '01
Total Building Hours: 1196
|
.... and Ross made sure they wont come
out.
|
|
| |
|
|
|
Date: Dec '01
Total Building Hours: 1228
|
So this is what we have achieved at the
end of the first year. It has filled all our weekends, but we
are very proud of what we have achieved. Though we hoped to have
been further along the challanges of working with heavy timber
and uneven levels takes time.
Our home has evolved meeting all the sustainable
objectives we set, and adding alot of personal experiences along
the way. We could not have planned a more rewarding year.
|
|
|
|
|
|
|
Date: Jan '02
Building Hours: 1232
|
We start this year with the floor bearers complete on the living
level. The levels for the joists will be challenging due to the
natural undulations of the bearers, but there will be no stopping
Mr Newton and his team.
|

|
|
|
|
|
Date: Jan '02
Building Hours: 1372
|
Joist ... and more notching .... but the floor is perfectly level.
With all of the notching into the bearers, we can get away without
blocking.
|

|
|
|
|
|
|
Date:Feb '02
Building Hours:1593
|
A suspended slab will be situated inside the north facing glass
doors. Concrete is a thermal mass. It will provide a heat sink
for the sun that enters onto this area in winter
|

|
|
|
|
|
Date: Apr '02
Building Hours: 1770
|
By notching the post for the floor boards, the post give the
impression that they are floating on this floor.
|

|
|
|
|
|
Date: May '02
Building Hours: 1800
|
Boards are all counter punched ready for sanding. The sawdust
from the sanding will be used to fill the punch holes. The timbers
will be burnished.
|
|
|
|
|
|
Date: July '02
Building Hours: 1864
|
Mortised post signals the start of the roof framing.
|
|
|
|
|
|
Date: July
02
Building Hours: 1934
|
No cranes, no nuts, no bolts. Just chain blocks, kopper logs
and some leverage.
Who said all the pyramid engineers were dead and buried.
|
|
|
|
|
|
Date: Aug '02
Building Hours: 2051
|
Thanks to the help of willing friends and family we maneuvered
the three Deveney water tanks into
position.
|
|
|
|
|
|
Date: Sept 02
Building Hours: 2267
|
And slowly the roof takes shape.
|
|
|
|
|
|
Date: Oct '02
Building Hours: 2500
|
Colins show how to bring roof framing, and cross bracing together
on a feature post
|
 |
|
|
|
|
Date: Oct '02
Building Hours:2471
|
Recycled floor joist are passed through a thicknesser and painted
with tung oil. These are now ready for use as exposed roof rafters.
|
|
|
|
|
|
Date: Dec '02
Total Building Hours: 2773
|
Years End. The king post is in position with plans for a roof
in 2003.
|
|
|
2003
|
|
|
|
Date: Jan '03
Building Hours: 2805
|
Ridge beam is lowered into position by a crane - perfect fit,
Colin and Ross never doubted it.
|
|
|
|
|
|
Date: Jan '03
Building Hours: 2805
|
Great opportunity to get our red gum log into the bathroom. You
will have to wait a bit longer for this one - one day it will
be our bathtub.
|
|
|
|
|
|
Date: Mar '03
Building Hours: 2917
|
The rafters now take their position - nestling into the hand
chiseled roof beams.
|
|
|
|
|
|
|
Date: Mar '03
Building Hours: 2917
|
Remember - these were the recycled floor joist which we have
plained and treated with tung oil. Rubbish one day beautiful the
next.
|
|
|
|
|
|
Date: June '03
Building Hours:
3151
|
Roof Framing Complete!
The celestory window is where Colin is waving on the right, Ross
on the left. The celestory faces north and will direct the low
winter sun deep into the house for warmth and natural daylighting.
|
|
|
|
|
|
Date: June '03
Building Hours:
3151
|
This has been our most challenging stage.
The work has all been done 12 meters above terra-firma. Chris
would never let either Colin or Ross up without being harnessed
to a pole. I think the fear of being left dangling from a harness
worried them more then a fall - but it seems to have worked.
Colin had his health set back last September - arthritis, fatigue,
fevers. Colin thinks it was a mosquito and does not feel they
are an important element of biodiversity anymore! We'll be taking
things slowly for a while.
|
|
|
|
|
|
Date:
July '03
Building Hours:
3277
|
Roofing starts!
Colin, Ross, Egon and Ari all get harnessed. Chris has given
them the challenge to drape the rush matting over the exposed
rafters, followed by the Air-Cell insulation, and then the off-white
roof sheeting. Work starts on the south roof.
The internal finish is looking very special.
|
|
|
|
|
|
Date:
Nov'03
|
Hard to appreciate the tricky work my boys have been up to in
the last 6 months.
Due to the pitch of the roof and the height above the steep
slope, we made a decision to finish the deck around the house
before attempting any further roofing.
So off they went again to find some big recycled pieces of timber.
|
|
|
|
|
|
Date:
Dec'03
|
Floor Boards
|
|
|
|
|
|
Date:
Dec'03
Building Hours:
3624
|
Struts, balustrade and floor boards from under.
|
|
|
|
|
|
Date:
Dec'03
|
The next stage is to finish the roof!
Then down to finish the boardwalk to give us access to the house
with out having to take straw bales up the ladder. Surely we will
be ready for the walls!
The straw bale walls will be infill on the top floor only. We
have been doing many test samples with our earth renders - and
are happy that we can finish our house in earth render both inside
and out.
|
|
|
2005
|
|
|
|
Date: 28 Dec '04
|
Straw Bales arrive.
Family who had turned up for a holidays suddenly found themselves
up in a straw bale tossing event. Thanks Bin and Alex.
The straw has been stored in a shed away from the risks of moisture
damage.
|
|
|
|
|
|
Date: 8
Jan'05
|
Colin and Egon spent 3 day screwing of the the roof and checking
it was ready for the PV panels to be installed
The white corrugated iron provides an ideal material for reflection
of heat and water harvesting.
Below the corrugated iron is AirCell insulation. This bubble
wrap like material is an ideal summer insulation - reflecting
heat and preventing it entering the building. It also traps air
in its small spaces - effectively providing winter heat escaping
the house in winter.
The roof has a large area facing the north, this aspect will soon
be used for the Photo Voltaic Cells that will power the Newton
House, and the solar hot water system.
|
|
|
|
|
|
Date: 11 Jan 05
|
16 solar panels take their position on the roof.
We are not connected to the grid.
We are now making all our power from the sun that lands on our
roof.
This web site will now be updated using solar power!
|
|
|
|
|
|
|
Feb 2005-
Feb 2006
|
We've needed to stop building for a while. Colin didn't getting
better the way the doctors told us. It has been 3.5 years. This
last year with lots of tests, probes and twinking.
Our time frame has never been what has driven us on this project.
I have always said it will take us about 10 years. So that puts
us on on schedule.
We have not been loitering though.... Check what is happening
in our garden.
|
|
|
|
|
|
March 2006
|
We've started again, downstairs on the utility floor. The room
at the back is the power room to support the solar panels.
Last weekend we finished to the floor for the water room. I love
the way the floor floats. This will hold the greywater system,
and pumps. The walls and roof will be finished downstairs for
these enclosures, then we are moving upstairs.
|

|
| |
|
|
| |
Rick did some wwoofing with us ... and we built this beautiful
a gabion rock table. The rock feature becomes the centre piece
of the table. Timbers are recycled hardwood rafters.
|
 |
| |
|
|
|
|
A 2 week working bee. This is the kick start we have needed to
get our project back on track. Our objective was to get the window
and door frames in. To complete the bottom and top plates of the
straw bale wall system. And to get the framing complete for the
east deck. With this we will be then ready to raise some straw
bale walls this year!
Window and door frames are made from recycled Queensland railway
sleepers.
|
 |
|
|
|
|
|
Oct '06
|
Colin lowers the bath in its final resting place.
|
 |
|
|
|
|
|
Oct '06
|
Skirting boards are in place and will double as the render stops
for the straw bale walls. These recycled blue gum bearers have
been sanded and finished with tung oil.
|
 |
|
|
|
|
|
Oct '06
|
The deck now wraps around the east side of the building. you
can just see Colin's signature struts coming from the poles below.
|
 |
|
|
|
|
|
Oct '06
|
This slab of camphor laurel has become the doorway sill.
|
 |
| |
|
|
| 6-7th January 2007 |
Our straw bale walls went up this weekend!!!
Straw Baling Images
|
|
| |
|
|